1菱形鐵網(60cm*80cm) 1.11.6.1 Diamond shape metal mesh (60cm x 80 cm)
2角鐵 1.11.6.2 Steel angle

 L.T型對接頭 L.T type snap joint
參考資料
(二)地坪加高工程1.2 Floor Re-levelling
2009-04-02 15:12:03 彌補
6小便斗 1.3.6 Urinal
7蹲式馬桶 1.3.7 Floor mount Toilet
8坐式馬桶 1.3.8 Toilet
9蓮蓬頭 1.3.9 Shower head
10洗面盆 1.3.10 Hand basin
11嘔吐槽 1.3.11 Vanity Basin
12電燈 1.3.12 Light fitting
一鋼棚新建工程1.1 New Metal Frame Shed
1挖方及棄土1.1.1 Excavation and earth refill
2柱基礎鋼筋及螺栓工程1.1.2 Column Footing, Steel reinforcement & Bolt Fixing

3H型鋼1.1.3 Steel H Section
4C型鋼 1.1.4 Steel C Section
53合一浪板1.1.5 Multi Layer Wafer Board
6鋁鋅清板1.1.6 Aluminium Zinc metal sheet
7烤漆快速捲門1.1.7 Galvanised Roller Room
8另料1.1.8 Other Materials
9工資1.1.9 Labour wages
10運費1.1.10 Transportation Cost

 噴漆裝備配督工資 Painting equipment setup labour cost

參考資料
1過濾裝備槽(含濾槽蕊) 1.11.4.1 Filtration Sink ( Include core filter)
2節制面板 1.11.4.2 Control interface
3吸氣箱(含電扇) 1.11.4.3 Suction Unit (include fan)
4抽風風鼓機 1.11.4.4 Air extraction unit
5方形風管 1.11.4.5 Square air duct
6吸氣箱圓形管 1.11.4.6 Suction unit circular duct
2009-04-02 15:48:26 增補

2009-04-02 16:07:04 彌補
參考資料
1、土建工程:1. Refurbishment
項次工作項目Project Item

參考資料
小計 Sub-total
進氣裝備 - Ventilation Unit
1抽風風鼓機 1.11.3.1 Air extraction unit
2圓形風管 1.11.3.2 Circular air duct
3方形出風口 1.11.3.3 Square Vent Air Grill
參考資料

 天花板菱形網架設工資 Diamond shape ceiling mesh labour cost

小計 Sub-Total

華頓翻譯社

(三)衛浴工程1.3 Bathroom fitting
烤漆溫控裝備 - Temperature Control Unit
參考資料
 對接頭 Snap joint
2009-04-02 16:03:23 增補
參考資料
參考資料
(八)雜項工程1.8 Miscellaneous
後面的項目有些華頓翻譯社不肯定是不是有相對的業界用詞. 若是這些是拿來對外招標用的, 那翻譯公司最好找專業的人再次確認(包羅原文的內容具體). 假如不是的話, 就拿來參考看看吧......
2009-04-02 15:13:01 彌補
五地板及木作工程 1.5 Flooring & Wood Work
1實木地板 1.5.1 Timber Floor
2木質衣櫃 1.5.2 Timber Wardrobe
小計 Sub-Total
噴漆過濾設備 - Paint Filtration System
另供給挂號全國室內裝修網址給大家參考
11*1.2吋角條 1.11.7.1 1x 1.2Inch edge board
23分(4*8)夾板 1.11.7.2 MDF board (4x8)
3塑鋁板(4*8) 1.11.7.3 ACP board (4x 8)
總計 Total – Sum
2009-04-02 15:13:27 增補
七防水工程 1.7 Water Proofing
1原辦公室(A-1)防水工程 1.7.1 Water proofing work to existing office (A-1)
2F段及大廠房中心防水 1.7.2 Water proofing for section F and main factory centre section.
參考資料
2009-04-02 15:49:49 補充
(十)噴漆間土木部分1.10 Painting Room Construction
噴烤漆過濾設備工資 Paint Filtration labour cost
參考資料
華頓翻譯社
1溫控.定時控制台 1.11.2.1 Temperature, Time Control Unit
2加溫裝備 1.11.2.2 Heating Unit
3送風電扇組 1.11.2.3 Ventilation Fan Unit
4白鐵外框架 1.11.2.4 Galvanised iron outer frame
5固定鐵架 1.11.2.5 Fixed metal frame
http://cpabm.cpami.gov.tw/search/bmd/InterDeco.jsp




2009-04-02 15:16:54 增補
22清洗溝(15mx1mx20m) 1.10.22 Floor Gully (15m x 1m x 20m)
23格柵板(15mx1m) 1.10.23 Floor Gully Cover
25地坪粉光(所有新澆置地坪) 1.10.25 Floor concrete polish (on all new concrete floor)
26牆面及矽酸鈣板面粉刷 1.10.26 Wall finish and plaster board rendering
2009-04-02 15:15:18 補充
5新設1B磚牆 1.10.5 New 1B block wall
6新設電動烤漆鐵捲門 1.10.6 Install new electrical roller door
7移裝舊電動鐵捲門 1.10.7 Remove existing electrical roller door
8新設分手式寒氣機3t 1.10.8 Install new 3T split A/C unit
9原水電分區箱移裝 1.10.9 Relocation of existing (????)
10新設t5燈組 1.10.10 Install new t5 type light fittings

參考資料
2009-04-02 15:14:11 增補
6洗手枱右高修繕 1.8.6 Hand basin repair
7原鐵門補綴 1.8.7 Repair on existing metal door.
8大廠加6'排水管 1.8.8 Install 6 water drain pipes for the factory
9天車拆遷組裝 1.8.9 Relocation and reassembly of existing crane
10鐵梯 1.8.10 Metal ladder
11資本收受接管站整修 1.8.11 Recycling Station Repair and Maintenance

1.interior Decoration Co.翻譯社 Ltd.

2.interior Fit Out Co., Ltd.

3.interior Design Co., Ltd.

4.interior Renovation Co.翻譯社 Ltd.


2009-04-02 15:13:07 補充
2砌1/2磚 1.6.2 ½ Block
31:3水泥粉刷 1.6.3 1:3 Plastering on Wall
4油漆(水性) 1.6.4 Acrylic Paint
5鋪貼60cmx60cm地磚 1.6.5 Lay tile (60cm x 60 cm)
 天花板菱形鐵網 - Diamond shape ceiling metal mesh
小計 Sub-Total
十噴漆間土木部份 1.10 Painting Construction
1地坪澆置(混凝土加級配) 1.10.1 Re-flooring ( concrete on refill)
2新設矽酸鈣板 1.10.2 Install new plaster board
3氣密窗 1.10.3 Air tight window
4木作部分 1.10.4 Wood work
小計Sub-Total

2009-04-02 15:11:51 增補
三衛浴工程 1.3 Bathroom Fittings
1敲除及清運 1.3.1 Demolition and waste removal
2地磚(20*20) 1.3.2 Floor tile (20 x 20)
3壁磚(20*25) 1.3.3 Wall tile (20 x 25)
4熱固性強化脂板內及隔屏 1.3.4 Thermal setting reinforced boards and partitions
5PVC天花板 1.3.5 PVC ceiling tile
小計 Sub-Total
2009-04-02 15:49:00 補充

1扭轉架軌道組 1.11.1.1 Spin rack & track set
2固定懸吊架 1.11.1.2 Fixed rack & track set
3連動式滑軌組 1.11.1.3 Coupling rack & track set
4連接桿.吊環組 1.11.1.4 Suspended Ring Set
5Y型鐵鈎 1.11.1.5 Y shape metal hook

華頓翻譯社翻譯社 奇摩, WWW
 五金另料 Other hardwares
二地坪加高工程1.2 Floor Re-levelling Work
1級配(含壓實)1.2.1 Refill (include compaction)
2混凝土1751.2.2 Concrete 175 Grade
3點焊鋼絲網1.2.3 Point Weld Steel Reinforcement Mesh
4模板1.2.4 Formwork
5泵浦車及潔淨工資1.2.5 Pump Truck and Cleaner Cost
6整體粉光1.2.6 Concrete Polishing
7伸縮縫1.2.7 Expansion Joint
8環氧樹酯1.2.8 Epoxy Resin
(六)泥作工程1.6 Wall & Plastering

參考資料
google查過
(四)冷氣工程1.4 Mechanical Service
華頓翻譯社
參考資料
六泥作工程 1.6 Wall & Plastering
1砌1B磚 1.6.1 1B Block
(七)防水工程1.7 Water Proofing
施工所在Project Site
2009-04-02 15:14:38 彌補
九空壓機改換 1.9 Air Compressor Replacement
1空壓機換裝 1.9.1 Replace Air Compressor

(十一)噴漆間裝備部分1.11 Painting Room Equipment

參考資料
(一)鋼棚新建工程1.1 New metal frame shed

2009-04-02 16:02:58 補充
2009-04-02 15:15:50 增補
11原有牆面敲除清運 1.10.11 Demolish existing wall finish and removal
12原有電力線修護 1.10.12 Maintenance on existing electrical cables
13新設雕欄(40mx1.2m)2"方管 1.10.13 Install new balustrade (40m x 1.2m, 2” SHS
14原有舊木門替換 1.10.14 Replace existing timber door
15新斜坡(含模板組立灌漿) 1.10.15 New ramp (include formwork and
參考資料
2009-04-02 15:12:23 增補
13新換鋁門窗 1.3.13 Supply and install new aluminium frame door and window
14新設側鋁內扇 1.3.14 Ventilation Aluminium Louver
整修工程明細表Refurbishment Project Item List
 牆面隔板木匠工資 Wall finish翻譯社 partition, wood word labour cost
2009-04-02 15:48:01 增補
十一噴漆間裝備部分 1.11 Painting Room Equipment
噴漆懸空鐵鈎吊架 - Suspended metal hook paint rack.
2009-04-02 15:49:24 彌補
小計Sub-Total
(九)空壓機替換1.9 Air Compressor Replacement
小計 Sub Total
參考資料
2009-04-02 15:48:40 彌補
參考資料
- 15 HP Air Compressor ( Include 400L empty drum barrel)
Q1:"室內裝修"有限公司英文應若何翻譯?
小計 Sub-Total
工程名稱整修工程Refurbishment Project Name:
四涼氣工程 1.4 Mechanical Service
12T離散式1對1寒氣 1.4.1 2T Split Air Conditioning Unit
25T冷氣遷徙 1.4.2 5T A/C unit relocation
參考資料
牆面隔板 - Wall Partition
2009-04-02 15:16:30 補充
16新設昇降梯 1.10.16 New lift
17原有2樓地坪澆置(10cm) 1.10.17 Concrete work on existing level 2 floor (10cm)
18新設木門 1.10.18 New timber door
19舊有窗框撤除 1.10.19 Remove existing window frames
20新設陰井(含開挖) 1.10.20 New Storm water drain (include excavation)
21模板組立(地坪) 1.10.21 Formwork for new floor
(五)地板及木作工程1.5 Flooring & Wood work
華頓翻譯社
華頓翻譯社

2009-04-02 15:13:48 彌補
八雜項工程 1.8 Miscellaneous
1空心木門改換200*210 1.8.1 Replace hollow timber door 200 x 210
2空心木門更換172*204 1.8.2 Replace hollow timber door 172 x 204
3空心木門81*206 1.8.3 Hollow timber door 81 x 206
4鋁窗90*270 1.8.4 Aluminum frame window 90 x 270
5釸酸鈣板隔間 1.8.5 Plaster board partition


空壓機15HP(含400L空桶)無油式空氣與水份離.噴漆專用



參考資料
1圓鐵.角鐵. 1.11.5.1 Circular steel angle, angle
2可動式鐵鈎.鐵方管 1.11.5.2 Mobile metal hook. Square metal duct
小計 Sub-Total
 高壓快速接頭 High pressure snap joint
參考資料
小計 Sub-Total

 4分鍍鋅管 8 in galvanise pipe (??)
參考資料
2、勞工安全衛生及情況維護費1% 2. Worker Work Place Health & Safety, and Environmental Protection.

3、營建綜合保險費0.5% 3. Construction All Risks Insurance

4、經管及利潤10% 4. Management Cost & Profit

5、稅金5% 5. Tax
六、總價 6. Total Sum
 
 滑軌旋轉噴漆吊架 - Spin rack suspended track